Rain washes out Revive I-5 weekend, but plenty more coming
UPDATE 7:37 a.m. Friday, May 13: Rain in the forecast means we have to postpone this work once again. Fingers crossed for dry weather soon. We will get word out when we know the next scheduled weekend of work.
By Tom Pearce
We didn’t get to Revive I-5 southbound near Spokane Street last weekend because of the rainy weather, but we’ll be back this weekend hoping for better conditions.
We’re planning to replace several joints near Spokane Street starting at about 7:30 p.m. Friday night, May 13. We’ve also adjusted our traffic plan a bit – the mainline of southbound I-5 will remain open, but we’ll begin to reduce the number of lanes south of I-90, eventually narrowing to a single lane.
Replacing expansion joints required a lot of work, including cutting old concrete. |
Work planned almost every weekend this summer
We still need about 16 weekends to replace 35 expansion joints on I-5, in addition to 10 others on the ramps that connect to the freeway. We can replace several joints on either the right lanes or left lanes in the same weekend, but the sheer number requires a lot of weekends that will stretch into early fall.
The left lanes will be closed all weekend south of I-90 to the Spokane Street area. |
As we saw last weekend, this work is weather-dependent. We use a polyester concrete to hold the joints in place. This is more durable that regular concrete, but it needs dry conditions to cure properly.
You can still get there
- Allow plenty of travel time.
- Use alternative routes like I-405 or SR 99 (remember the toll)
- Consider light rail or buses
- Travel early (before 8 a.m.) or late (after 8 p.m.)